The Del Mar ADU application

Del Mar processes ADUs ministerially, with a building permit and, where required, an Administrative Coastal Development Permit. Here's what Chapter 30.91 asks you to submit (Del Mar Municipal Code Chapter 30.91 (June 2025)).

Craftsman ADU with stone porch columns
Craftsman ADU with stone porch columns

Submittal checklist (ADU)

JrADU submittal

Timeline and process

StepRule
DecisionMinisterial approval or disapproval within state time limits (Gov. Code §66317: 60 days)
DisapprovalWritten comments listing deficiencies and how to fix them
With a new houseADU reviewed before the house's hearing; may be held until the house is acted on, without discretionary review
Deed restrictionRecorded before the building permit
ExpirationTwo years after issuance without a certificate of occupancy

Source: DMMC §30.91.030.

Building a new house and ADU together

If you're applying for a new house and an ADU at the same time, the ADU application is submitted before the house's public hearing and shown on the house plans. The city may hold the ADU until it acts on the house, but the ADU itself gets no discretionary review or hearing, and the house's decision maker can't consider the pending ADU. If you ask for a delay, the 60-day clock pauses.

After approval

What's in the packet

Engineering review

ProjectEngineering review?
New attached ADUYes
New detached ADUYes
ADU inside the house or an existing accessory structureNo
Garage converted to an ADUNo

Source: Del Mar ADU Application Packet, Engineering ADU Plan Requirements.

Construction notes the plans carry

Equipment and truck operations are limited to 7 a.m. to 6 p.m., Monday through Friday, with none on Sundays or city holidays. Archaeological finds stop work until the city authorizes resumption. The limit of work is marked in the field before clearing, and Engineering does a final site inspection.

Also checked Oct 14, 2026: Del Mar ADU Application Packet (Rev. 2024) · HCD ADU Handbook (March 2026).

Sources, checked Oct 14, 2026: Del Mar Municipal Code Chapter 30.91 (June 2025) · City of Del Mar ADU page.

Questions

What does Del Mar require with an ADU application?

The ADU Application Packet, fees, and plans including a site plan with protected trees, sections, elevations, floor plan, utility information, standard notes and a construction parking plan.

How long does a Del Mar ADU permit last?

Two years after issuance unless a certificate of occupancy is issued.